A client wants an upgrade that is not in the original contract but does not want to pay more. How should you handle this?
-
A
Add the upgrade to maintain goodwill without mention
-
B
Explain that changes in scope require a change order and additional cost
-
C
Refuse the upgrade without explanation
-
D
Finish the project and add the charge to the final invoice as a surprise