NASCLA Business Organization and Operations 2 — Questions and Answers
Question 1: Which of the following best describes 'bonding capacity' for a construction company?
- The total amount of insurance the company carries
- The maximum dollar amount of work a surety company will bond for a contractor at one time (Correct answer)
- The company's ability to hire subcontractors
- The contractor's line of credit with a bank
Correct answer: The maximum dollar amount of work a surety company will bond for a contractor at one time
Bonding capacity is the maximum aggregate project value that a surety company will guarantee for a contractor, based on the contractor's financial strength, experience, and management.
Question 2: What is a 'prequalification' process in construction procurement?
- A meeting held before construction begins
- An owner's evaluation of a contractor's qualifications, financial stability, and experience before allowing them to bid (Correct answer)
- A test required before obtaining a contractor's license
- A government review of construction plans before permit issuance
Correct answer: An owner's evaluation of a contractor's qualifications, financial stability, and experience before allowing them to bid
Prequalification is a process where owners evaluate contractors on financial strength, bonding capacity, experience, safety record, and references before permitting them to submit bids.
Question 3: What is the primary purpose of maintaining accurate payroll records in construction?
- To impress potential clients with financial documentation
- To comply with wage and hour laws, workers' comp audits, prevailing wage requirements, and tax obligations (Correct answer)
- To calculate the contractor's bonding capacity
- To determine material quantities for future projects
Correct answer: To comply with wage and hour laws, workers' comp audits, prevailing wage requirements, and tax obligations
Accurate payroll records are required for compliance with wage and hour laws, workers' compensation premium audits, prevailing wage certifications, unemployment insurance, and IRS reporting.
Question 4: A contractor's 'markup' on a project covers which of the following?
- Only direct material costs
- Overhead expenses and profit added to direct costs to determine the contract price (Correct answer)
- The cost of the contractor's personal vehicle
- Workers' compensation insurance only
Correct answer: Overhead expenses and profit added to direct costs to determine the contract price
Markup is the percentage added to direct project costs to cover the contractor's overhead expenses and desired profit margin, resulting in the final contract price.
Question 5: Which of the following is a key advantage of using a written subcontract agreement?
- It eliminates the need for the subcontractor to carry insurance
- It clearly defines scope, payment, schedule, and responsibilities, reducing disputes (Correct answer)
- It automatically transfers all liability to the subcontractor
- It replaces the need for a performance bond
Correct answer: It clearly defines scope, payment, schedule, and responsibilities, reducing disputes
Written subcontract agreements reduce disputes by clearly defining scope of work, payment terms, schedule, insurance requirements, indemnification, and dispute resolution procedures.
Question 6: What does 'FICA' stand for, and what does it fund?
- Federal Insurance Contributions Act — funds Social Security and Medicare (Correct answer)
- Federal Income Contribution Act — funds federal highway construction
- Federal Incorporated Contractors Act — funds contractor licensing
- Financial Insurance and Credit Act — funds small business loans
Correct answer: Federal Insurance Contributions Act — funds Social Security and Medicare
FICA stands for the Federal Insurance Contributions Act, requiring both employees and employers to contribute to Social Security (6.2%) and Medicare (1.45%) through payroll taxes.
Which of the following best describes 'bonding capacity' for a construction company?