During the utility interconnection application process, what typically triggers a 'Supplemental Review' (or detailed study)?
-
A
Use of string inverters instead of microinverters
-
B
The system fails initial fast-track screening due to potential adverse grid impacts
-
C
All commercial systems regardless of grid impact
-
D
Use of battery storage in addition to solar panels