During PV system commissioning, you measure an open-circuit voltage significantly higher than the STC-rated Voc. What is the most likely cause?
-
A
Shading on one or more modules
-
B
Ambient temperature is much lower than 25°C STC
-
C
A bypass diode has failed short
-
D
The inverter is in sleep mode