Which commissioning test confirms that a ground fault detection and interruption (GFDI) device on a grounded PV system is functioning correctly?
-
A
Applying a temporary resistive ground fault and verifying the device trips
-
B
Measuring Voc of each string and comparing to spec
-
C
Verifying the DC disconnect opens under full load
-
D
Testing continuity of the equipment grounding conductors