In MRP-driven environments, what is the primary purpose of time fencing in the Master Production Schedule (MPS)?
-
A
To limit the number of open purchase orders
-
B
To stabilize the near-term schedule by restricting automatic changes
-
C
To separate production from distribution planning
-
D
To define safety stock replenishment triggers