A buyer notices that MRP has generated planned orders for a purchased item even though sufficient on-hand stock exists. The most likely cause is:
-
A
An incorrect low-level code assignment
-
B
Inaccurate inventory records overstating on-hand quantities
-
C
The lot-sizing rule requiring a minimum order quantity
-
D
An expired supplier contract reducing available supply