(MRP) MRP Certified Agents Practice Test

MRP Data Analysis & System Implementation 4

Free · Instant Results

A multi-level BOM has a finished good (Level 0), sub-assembly (Level 1), and raw material (Level 2). If 100 units of the finished good are needed, the sub-assembly has a quantity per of 2, and the raw material has a quantity per of 3, how many units of raw material are required?
▶ Start Practice Test