In MRP analysis, what does a 'firm planned order' (FPO) allow a planner to do that a standard planned order does not?
-
A
Automatically convert to a purchase order
-
B
Prevent the MRP system from automatically rescheduling the order
-
C
Trigger a capacity requirements planning run
-
D
Override vendor lead times