When analyzing MRP output, a planner notices that planned orders are being generated for items already in stock above safety stock levels. What is the most likely cause?
-
A
Incorrect lead times in the item master
-
B
The safety stock level is set higher than the on-hand quantity
-
C
Lot sizing rules are creating excess demand
-
D
The BOM is missing a component