โ† All MRP Flashcard Decks

Material Requirements Planning Fundamentals Flashcards

7 cards from real MRP practice questions. Tap to flip, then mark Knew It or Still Learning โ€” missed cards come back until you master them.

Read the first 7 Material Requirements Planning Fundamentals flashcards as text
  1. The Economic Order Quantity (EOQ) lot-sizing rule minimizes the sum of which two cost categories?

    Answer: Ordering costs and carrying costs

    EOQ balances ordering (or setup) costs against inventory carrying (holding) costs to find the most cost-effective order quantity.

  2. What is the effect of increasing safety stock levels in an MRP system?

    Answer: Increases net requirements and planned order quantities

    Higher safety stock increases the projected on-hand target, which raises net requirements and therefore the planned order quantities generated by MRP.

  3. Which MRP output is used by purchasing to create purchase orders?

    Answer: Planned order releases for purchased items

    Planned order releases for purchased items are the MRP output that triggers the creation of purchase orders to external suppliers.

  4. A 'pegging' report in MRP is used to:

    Answer: Trace a component's demand back to its parent requirement

    Pegging links a lower-level component requirement back through the BOM to the specific parent orders or customer demands that caused it.

  5. Low-level coding in a BOM ensures that MRP:

    Answer: Calculates requirements for a component after all its parents have been planned

    Low-level coding assigns each part a code equal to the lowest level it appears, ensuring MRP nets all parent demands before planning that component.

  6. What problem does 'nervousness' describe in an MRP system?

    Answer: Frequent and disruptive changes to planned orders caused by small demand fluctuations

    MRP nervousness refers to the tendency of the system to generate large, cascading changes to the plan in response to even minor changes in demand or supply.

  7. Which technique is used to stabilize an MRP plan and reduce system nervousness?

    Answer: Implementing time fences on the MPS

    Time fences restrict automatic changes to the MPS within a defined near-term window, preventing constant replanning and stabilizing downstream MRP schedules.

Material Requirements Planning Fundamentals Flashcards โ€” MRP Study Cards with Answers