Under Maryland law, a change order that increases the cost or scope of a home improvement project must be:
-
A
Submitted to the MHIC for approval before work proceeds
-
B
In writing and signed by both the contractor and the homeowner
-
C
Notarized by a licensed notary public
-
D
A verbal agreement confirmed in a follow-up email