A Windows Server 2008 network project is entering its final testing phase. Which communication practice ensures all stakeholders are aligned on go-live readiness?
-
A
Announce go-live via a spontaneous chat message on the day of deployment
-
B
Hold a go/no-go meeting with stakeholders, share test results, and obtain explicit sign-off before proceeding
-
C
Skip the meeting to save time since testing passed internally
-
D
Send a go-live email after the change is already complete