← All Manufacturing and Production Flashcard Decks

Production Planning and Scheduling Flashcards

6 cards from real Manufacturing and Production practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 6 Production Planning and Scheduling flashcards as text
  1. The Theory of Constraints (TOC) prescribes which sequence of steps?

    Answer: Identify, Exploit, Subordinate, Elevate, Repeat

    TOC's five focusing steps guide organizations to identify and systematically improve their production constraints.

  2. What is 'work-in-process' (WIP) inventory?

    Answer: Materials that have been started but not yet completed

    WIP consists of partially completed products currently being processed or waiting between production steps.

  3. Forward scheduling in production means:

    Answer: Scheduling jobs as early as possible from the current date

    Forward scheduling starts from the earliest available date and schedules each operation forward in time.

  4. What is the purpose of a 'dispatch list' in production scheduling?

    Answer: A prioritized list telling operators which jobs to work on next at each work center

    A dispatch list tells shop floor operators the priority sequence of jobs to process, ensuring the right work is done in the right order.

  5. Machine utilization is calculated as:

    Answer: Actual run time / available time × 100%

    Machine utilization measures the percentage of available time that a machine is actually producing, excluding downtime.

  6. What is 'changeover time' in production scheduling?

    Answer: The time required to switch production from one product to another

    Changeover time is the non-productive time spent reconfiguring equipment between different production runs.