During an inspection, you find that a direct-burial landscape lighting cable run crosses under a concrete patio without conduit protection. What is the required corrective action?
-
A
No action needed if the cable is rated for direct burial
-
B
The cable must be re-routed through Schedule 40 PVC or rigid conduit under hardscape
-
C
Seal the cable entry points with silicone and leave in place
-
D
Only conduit is required under driveways, not patios