LEED (Leadership in Energy and Environmental Design Certification) Sustainable Sites 3 — Questions and Answers
Question 1: A project is located in a dense urban area and has no available land for on-site open space. How can it still earn the LEED Open Space credit?
- By providing a rooftop green space accessible to building occupants (Correct answer)
- By paying into a local parks fund equivalent to the required open space area
- By partnering with an adjacent property to share their open space
- By demonstrating that on-site open space is not feasible due to zoning
Correct answer: By providing a rooftop green space accessible to building occupants
LEED allows vegetated rooftop spaces accessible to occupants to count toward the Open Space credit when ground-level open space is constrained by urban conditions.
Question 2: Under the LEED Sustainable Sites prerequisite for Construction Activity Pollution Prevention, which document must be implemented during construction?
- A Stormwater Pollution Prevention Plan (SWPPP) (Correct answer)
- An Environmental Impact Assessment (EIA)
- A Habitat Conservation Plan (HCP)
- A Best Management Practices (BMP) manual approved by the EPA
Correct answer: A Stormwater Pollution Prevention Plan (SWPPP)
The prerequisite requires implementation of an erosion and sedimentation control plan that meets or exceeds local regulations, typically documented as a SWPPP.
Question 3: For the Heat Island Reduction credit, what is the minimum Solar Reflectance Index (SRI) required for a steep-sloped roofing material (slope > 2:12)?
- SRI of 29
- SRI of 39
- SRI of 64
- SRI of 78 (Correct answer)
Correct answer: SRI of 78
LEED requires steep-sloped roofs (slope greater than 2:12) to have an SRI of at least 78 to qualify for the non-roof heat island reduction pathway.
Question 4: Which of the following is NOT a qualifying strategy under the LEED Rainwater Management credit?
- Bioretention cells (rain gardens)
- Cisterns for rainwater harvesting and reuse
- Conventional storm sewers that discharge directly to a municipal system (Correct answer)
- Permeable pavement with infiltration
Correct answer: Conventional storm sewers that discharge directly to a municipal system
Conventional storm sewers that simply redirect runoff to municipal systems do not manage rainwater on site and therefore do not qualify as LID strategies for this credit.
Question 5: A mixed-use LEED project includes both retail and residential uses. Under the Surrounding Density and Diverse Uses credit, what is the purpose of the 'diverse uses' component?
- To ensure the building itself contains at least four different use types
- To reward proximity to a variety of community amenities within walking distance (Correct answer)
- To require the project to provide services for underserved populations nearby
- To encourage mixed-income housing within the project boundary
Correct answer: To reward proximity to a variety of community amenities within walking distance
The diverse uses component rewards projects located near a variety of retail, civic, and community uses within a short walk, reducing the need for vehicle trips.
Question 6: Under the LEED Place-Based Policies approach for Rainwater Management, what must a project demonstrate to earn the credit?
- Adoption of LEED standards at the municipal level for all new development
- Compliance with a locally adopted stormwater management plan that addresses quantity and quality (Correct answer)
- A 25% reduction in site runoff compared to pre-development hydrology
- Installation of green infrastructure covering at least 20% of the site area
Correct answer: Compliance with a locally adopted stormwater management plan that addresses quantity and quality
Projects can use an alternative compliance path by demonstrating conformance with a locally adopted, comprehensive stormwater management plan that addresses both runoff quantity and quality.
Question 7: A developer is evaluating two sites. Site A is a greenfield outside the urban growth boundary; Site B is an infill site in a walkable urban neighborhood. Which LEED SS credit most directly penalizes choosing Site A over Site B?
- High Priority Site
- Surrounding Density and Diverse Uses (Correct answer)
- Site Assessment
- Protect or Restore Habitat
Correct answer: Surrounding Density and Diverse Uses
The Surrounding Density and Diverse Uses credit rewards projects in densely developed, walkable areas, making greenfield sites outside urban boundaries ineligible for this credit.
A project is located in a dense urban area and has no available land for on-site open space.
How can it still earn the LEED Open Space credit?