Under LEED BD+C v4, what is the primary purpose of the 'Integrative Process' credit?
-
A
To require LEED AP team members on every project
-
B
To encourage early analysis of energy and water systems to identify interrelationships and improve performance
-
C
To mandate a design charrette attended by all stakeholders
-
D
To document how the project achieves all prerequisites