LARE LARE Stormwater Management 2 — Questions and Answers
Question 1: Which stormwater BMP is specifically designed to treat road runoff containing high concentrations of heavy metals and petroleum hydrocarbons?
- Constructed wetland
- Vegetated filter strip
- Dry extended detention basin
- Bioretention cell with amended soil media (Correct answer)
Correct answer: Bioretention cell with amended soil media
Bioretention cells with engineered soil media are particularly effective at removing heavy metals and hydrocarbons through adsorption and biological uptake.
Question 2: What is the primary purpose of a forebay in a stormwater retention pond?
- To aerate the water before it enters the main pool
- To capture coarse sediment before it enters the main pond (Correct answer)
- To regulate overflow during large storm events
- To provide habitat for aquatic vegetation
Correct answer: To capture coarse sediment before it enters the main pond
A forebay is a smaller settling chamber at the inlet of a stormwater pond that captures coarse sediment, reducing maintenance needs for the main pool.
Question 3: Under the Rational Method (Q = CiA), if the drainage area doubles but the runoff coefficient and rainfall intensity remain constant, what happens to peak runoff?
- It remains the same
- It doubles (Correct answer)
- It quadruples
- It increases by the square root of 2
Correct answer: It doubles
In the Rational Method, peak runoff Q is directly proportional to area A, so doubling A doubles Q when C and i are constant.
Question 4: Which approach does Low Impact Development (LID) primarily emphasize for managing stormwater?
- Centralizing large detention basins at the downstream end of the watershed
- Treating stormwater at the source through distributed, small-scale practices (Correct answer)
- Increasing pipe sizing to convey runoff faster
- Applying chemical treatments to neutralize pollutants
Correct answer: Treating stormwater at the source through distributed, small-scale practices
LID emphasizes distributed, small-scale practices that manage runoff close to its source, mimicking pre-development hydrology.
Question 5: A site has a pre-development CN of 58 and a post-development CN of 80. What is the primary concern this change reflects?
- Decreased evapotranspiration rates
- Significantly increased runoff volume and peak flow (Correct answer)
- Reduced groundwater contamination risk
- Improved water quality through increased contact time
Correct answer: Significantly increased runoff volume and peak flow
A higher Curve Number (CN) indicates greater imperviousness, resulting in significantly more runoff volume and higher peak flows after development.
Question 6: Which factor is most critical when sizing a stormwater infiltration trench?
- Depth to seasonal high groundwater table (Correct answer)
- Proximity to impervious surfaces
- Slope of the contributing drainage area
- Vegetation type surrounding the trench
Correct answer: Depth to seasonal high groundwater table
Infiltration trenches must maintain adequate separation (typically 2-4 feet) from the seasonal high groundwater table to prevent groundwater contamination and ensure adequate storage.
Question 7: What is 'channel protection volume' (Cpv) in stormwater management design?
- The storage needed to prevent overtopping of channel banks during the 100-year storm
- Storage designed to control frequent runoff events that cause stream channel erosion (Correct answer)
- The volume of sediment deposited annually in a stream channel
- The minimum channel cross-section required for fish passage
Correct answer: Storage designed to control frequent runoff events that cause stream channel erosion
Channel protection volume (Cpv) is designed to control the frequent 1-year storm event runoff, which is the primary driver of bank erosion and channel instability.
Which stormwater BMP is specifically designed to treat road runoff containing high concentrations of heavy metals and petroleum hydrocarbons?