A contractor's bid is 20% below the engineer's estimate, and all other bids cluster within 5% of each other. What is the most prudent action for the owner's team?
-
A
Award to the low bidder immediately because the owner saves money
-
B
Investigate the low bid for potential errors or omissions before awarding
-
C
Reject all bids and rebid the project
-
D
Award to the second-lowest bidder as the low bid appears unreliable