During construction administration, a contractor submits a Request for Information (RFI) about an apparent conflict between the civil drawings and the landscape drawings. What is the landscape architect's primary responsibility?
-
A
Issue a change order immediately to resolve the conflict
-
B
Review the conflict and issue a written response clarifying design intent
-
C
Direct the contractor to use the civil drawings as the controlling document
-
D
Notify the owner and halt construction until the conflict is resolved