LARE LARE Bidding and Contract Administration 5 — Questions and Answers
Question 1: What is the purpose of a payment bond (labor and material bond) on a landscape construction project?
- To guarantee the contractor completes the project
- To ensure that subcontractors and suppliers are paid (Correct answer)
- To protect the owner from contractor bankruptcy
- To fund project contingencies when change orders exceed the budget
Correct answer: To ensure that subcontractors and suppliers are paid
A payment bond guarantees that the bonding company will pay subcontractors, laborers, and material suppliers if the general contractor fails to pay them.
Question 2: A 'no-damage-for-delay' clause in a construction contract means:
- The contractor cannot claim liquidated damages if the project is delayed
- The contractor may only recover additional time, not additional money, for owner-caused delays (Correct answer)
- Neither party can recover costs when delays are caused by weather
- The contractor waives all delay claims by signing the contract
Correct answer: The contractor may only recover additional time, not additional money, for owner-caused delays
A no-damage-for-delay clause limits the contractor's remedy for owner-caused delays to time extensions only, prohibiting monetary claims for delay damages.
Question 3: During construction administration, the landscape architect observes work that does not conform to the contract documents. The most appropriate immediate action is to:
- Stop work immediately and notify the building department
- Issue a written nonconformance notice to the contractor and notify the owner (Correct answer)
- Negotiate an acceptable compromise with the contractor on-site
- Deduct the value of defective work from the next payment application
Correct answer: Issue a written nonconformance notice to the contractor and notify the owner
The landscape architect should document the nonconformance in writing, notify the contractor of required corrective action, and keep the owner informed.
Question 4: Which type of contract delivery method allows the landscape architect and contractor to work concurrently, often shortening the project schedule?
- Design-bid-build
- Construction manager at-risk
- Fast-track design-build (Correct answer)
- Integrated project delivery
Correct answer: Fast-track design-build
Fast-track design-build overlaps design and construction phases, allowing early construction packages to begin before the entire design is complete, compressing the overall schedule.
Question 5: A final punch list is typically prepared and distributed at what project milestone?
- After the contractor submits the schedule of values
- At or shortly before substantial completion (Correct answer)
- After the final certificate for payment is issued
- When the contractor requests final inspection
Correct answer: At or shortly before substantial completion
The punch list is prepared at or near substantial completion and documents all remaining incomplete or defective items the contractor must correct before final payment.
Question 6: Under AIA contract documents, the landscape architect's authority to reject work is most accurately described as:
- Absolute — the landscape architect can halt all work at any time for any reason
- Limited — rejection requires prior owner approval before the contractor is notified
- Professional — the landscape architect can reject work that does not conform to contract documents (Correct answer)
- Advisory — rejection is a recommendation only and the owner makes the final decision
Correct answer: Professional — the landscape architect can reject work that does not conform to contract documents
AIA documents grant the architect/landscape architect the authority to reject work that does not conform to the contract documents as part of their design professional role.
Question 7: When a landscape architect is comparing bids, one bid is significantly lower than all others. The best practice is to:
- Award immediately to capture cost savings for the owner
- Investigate the low bid for potential errors or missing scope before recommending award (Correct answer)
- Reject the low bid as non-responsive and award to the second-lowest bidder
- Require the low bidder to increase their bid bond before award
Correct answer: Investigate the low bid for potential errors or missing scope before recommending award
A significantly low bid should be analyzed to determine whether it reflects an error, omitted scope, or a genuine competitive advantage before recommending award.
What is the purpose of a payment bond (labor and material bond) on a landscape construction project?