A landscape architect discovers a significant discrepancy in the bid documents after bids have been submitted but before award. What is the correct course of action?
-
A
Award the contract and issue a change order later
-
B
Reject all bids and re-advertise with corrected documents
-
C
Issue an addendum and request revised bids from all bidders
-
D
Award to the lowest bidder and negotiate the discrepancy