A geotechnical report indicates that a project requires 10,000 cubic yards of compacted fill. The native soil to be used for the fill has a swell factor of 20% when excavated and a shrinkage factor of 10% from its original bank state when compacted. To achieve the required 10,000 cubic yards of compacted fill, approximately how much native soil must be excavated?