A landscape architect discovers a significant error in the irrigation plan five days before the scheduled bid opening. To ensure fairness and clarity for all potential bidders, what is the most appropriate action to take?
-
A
Issue a formal addendum to all parties who have received the bidding documents.
-
B
Wait for the winning contractor to identify the error and then issue a change order.
-
C
Verbally inform each bidder of the correction as they submit their bid.
-
D
Cancel the current bid process and re-issue the entire set of documents at a later date.