KDOT Highway & Bridge Inspection Procedures 2 — Questions and Answers
Question 1: During a routine bridge inspection, an inspector notices efflorescence on a concrete pier. What does this indicate?
- Surface paint deterioration
- Water infiltration and potential leaching of calcium hydroxide (Correct answer)
- Normal concrete curing process
- Alkali-silica reaction only
Correct answer: Water infiltration and potential leaching of calcium hydroxide
Efflorescence is a white crystalline deposit caused by water moving through concrete and leaching calcium hydroxide to the surface, indicating moisture infiltration.
Question 2: What is the primary purpose of the AASHTO Manual for Bridge Element Inspection (MBEI)?
- To provide bridge design specifications
- To standardize element-level condition ratings and quantities (Correct answer)
- To establish bridge load ratings
- To define contractor bid procedures
Correct answer: To standardize element-level condition ratings and quantities
The MBEI establishes standardized element-level condition states and quantities for consistent bridge inspection data collection across agencies.
Question 3: A Kansas inspector observes transverse cracking in a reinforced concrete bridge deck at regular intervals. The most likely cause is:
- Overloading by heavy trucks
- Shrinkage and thermal stresses during curing (Correct answer)
- Alkali-silica reaction
- Freeze-thaw deterioration
Correct answer: Shrinkage and thermal stresses during curing
Regularly spaced transverse cracks in bridge decks are typically caused by concrete shrinkage and thermal contraction stresses during and after curing.
Question 4: Under FHWA regulations, what is the maximum interval allowed between routine bridge inspections for most bridges?
- 12 months
- 18 months
- 24 months (Correct answer)
- 36 months
Correct answer: 24 months
FHWA regulations (23 CFR 650) require routine bridge inspections at intervals not exceeding 24 months for most bridges.
Question 5: When inspecting a steel girder bridge, spalling of the concrete deck over a girder flange is most likely caused by:
- Excessive live load deflection
- Corrosion of embedded reinforcing steel causing expansion (Correct answer)
- Poor aggregate quality
- Thermal expansion of the girder
Correct answer: Corrosion of embedded reinforcing steel causing expansion
Corrosion of reinforcing steel expands the metal, generating internal pressure that causes the overlying concrete to crack and spall.
Question 6: Which NBI condition rating indicates that a bridge element has suffered serious deterioration or loss of cross-section but is still functional?
- Rating 4 (Correct answer)
- Rating 5
- Rating 6
- Rating 7
Correct answer: Rating 4
NBI condition rating 4 (Poor) indicates serious deterioration or section loss but the bridge element is still functional, not imminently failing.
Question 7: An inspector performing an underwater bridge inspection encounters zero-visibility conditions. The appropriate action is to:
- Cancel the inspection and reschedule
- Use tactile (touch) inspection methods per KDOT protocols (Correct answer)
- Estimate conditions based on above-water findings
- Document as 'not inspected' and move on
Correct answer: Use tactile (touch) inspection methods per KDOT protocols
When underwater visibility is zero, KDOT and FHWA protocols require tactile inspection methods where divers physically feel elements to assess conditions.
During a routine bridge inspection, an inspector notices efflorescence on a concrete pier.
What does this indicate?