A plant's maintenance records show a component failing repeatedly every 3–4 months. The BEST long-term corrective action is to:
-
A
Increase the PM interval to match the failure frequency
-
B
Perform root cause analysis (RCA) to eliminate the underlying cause
-
C
Stock more spare parts to reduce downtime
-
D
Assign a dedicated technician to monitor that component