Preventive Maintenance & Troubleshooting Flashcards

7 cards from real ITMC practice questions. Tap to flip, then mark Knew It or Still Learning โ€” missed cards come back until you master them.

Read the first 7 Preventive Maintenance & Troubleshooting flashcards as text
  1. A technician is using the 'run-to-failure' maintenance strategy for a component. This approach is MOST appropriate when:

    Answer: The component is non-critical and its failure has no safety or production impact

    Run-to-failure is cost-effective only for non-critical components whose failure causes no safety hazard or significant production loss.

  2. Which type of coupling is MOST forgiving of angular misalignment between two shafts?

    Answer: Gear coupling

    Gear couplings can accommodate both angular and parallel misalignment through the meshing of crowned gear teeth, making them highly flexible.

  3. A plant uses oil analysis as a predictive maintenance tool. An increase in ferrous metal particle count in a gearbox sample indicates:

    Answer: Abnormal wear of steel gear components

    Elevated ferrous particle counts in oil analysis indicate that steel or iron components inside the gearbox are experiencing abnormal wear.

  4. During a PM task, a technician notices a gearbox is operating significantly hotter than its normal temperature baseline. What is the MOST logical first step?

    Answer: Check the lubricant level and condition

    Low lubricant level or degraded oil is the most common cause of elevated gearbox temperature and should be verified before taking more invasive action.

  5. What is the PRIMARY purpose of a CMMS (Computerized Maintenance Management System) in a PM program?

    Answer: To schedule, track, and document maintenance activities and asset history

    A CMMS centralizes the scheduling, tracking, and documentation of maintenance work orders and equipment history to optimize PM programs.

  6. A technician measures the current draw of a three-phase motor and finds one phase is drawing significantly more current than the other two. The MOST likely cause is:

    Answer: An open or high-resistance phase in the supply circuit

    An open or high-resistance connection on one phase forces the other phases to carry more current to compensate, causing current imbalance.

  7. In the context of PM scheduling, what does the term 'condition-based maintenance' (CBM) mean?

    Answer: Maintenance triggered by actual equipment condition data

    Condition-based maintenance uses real-time or periodic equipment condition data (vibration, temperature, oil analysis) to trigger maintenance only when needed.