ITIL ITIL Problem Management & Root Cause Analysis 2 — Questions and Answers
Question 1: What is the relationship between Problem Management and Change Management?
- Problem Management replaces Change Management for urgent fixes
- Problem Management raises Requests for Change (RFCs) to implement permanent fixes (Correct answer)
- Change Management approves problem records before investigation begins
- They operate completely independently with no interaction
Correct answer: Problem Management raises Requests for Change (RFCs) to implement permanent fixes
Problem Management raises RFCs through Change Management to implement permanent fixes for known errors and resolved problems.
Question 2: What is the purpose of a 'workaround' in ITIL Problem Management?
- A permanent solution to a problem
- A temporary measure to reduce or eliminate the impact of an incident or problem until a permanent fix is available (Correct answer)
- A configuration change that prevents incidents from recurring
- A report submitted to management on problem status
Correct answer: A temporary measure to reduce or eliminate the impact of an incident or problem until a permanent fix is available
A workaround is a temporary measure that reduces or eliminates the impact of an incident or problem before a permanent fix is implemented.
Question 3: Which root cause analysis tool visually maps potential causes of a problem in categories?
- 5 Whys technique
- Pareto chart
- Ishikawa (fishbone) diagram (Correct answer)
- Fault tree analysis
Correct answer: Ishikawa (fishbone) diagram
The Ishikawa (fishbone) diagram visually maps potential causes of a problem across categories such as people, processes, technology, and environment.
Question 4: When should a problem record be closed in ITIL?
- As soon as a workaround is found
- When all incidents linked to it have been resolved
- Only after a permanent fix has been implemented and verified (Correct answer)
- When the problem has been escalated to a third-party vendor
Correct answer: Only after a permanent fix has been implemented and verified
A problem record should be closed only after a permanent fix has been implemented and verified, ensuring the root cause has been eliminated.
Question 5: What is a 'Problem Review' conducted after a major problem?
- A meeting to assign blame for the incident
- An analysis to identify lessons learned and prevent recurrence (Correct answer)
- A financial audit of costs incurred during the incident
- A review of SLA compliance following service restoration
Correct answer: An analysis to identify lessons learned and prevent recurrence
A Problem Review (or post-implementation review) is conducted to identify lessons learned and improvements to prevent similar problems in the future.
Question 6: Which ITIL concept describes categorizing problems based on the number of incidents they cause and their business impact?
- Problem prioritization (Correct answer)
- Known error cataloging
- Incident trending
- Service impact analysis
Correct answer: Problem prioritization
Problem prioritization uses the frequency of related incidents and business impact to determine which problems should be investigated first.
What is the relationship between Problem Management and Change Management?