What is the correct first step in the typical sequence for a lockout/tagout procedure on a machine that is running?
-
A
Apply the lock to the energy-isolating device
-
B
Notify affected employees, then shut the machine down by its normal stopping procedure
-
C
Verify zero energy by attempting to start the machine
-
D
Remove the tag from the previous shift