Which stakeholder is typically responsible for issuing a Certificate of Completion or Mechanical Completion in an automation project?
-
A
The instrument technician performing calibrations
-
B
The project owner or their designated representative after verifying all completion criteria are met
-
C
The DCS vendor's commissioning engineer
-
D
The process safety engineer