What legal requirements should be referenced in the risk assessment project?
Answer: Relevant legislation such as HSWA 1974, Management Regulations 1999, and any specific regulations applicable to the hazards identified
The project should reference relevant legislation including: the HSWA 1974 (general duties), the Management Regulations 1999 (risk assessment duty), and specific regulations relevant to identified hazards (e.g., COSHH for chemicals, Manual Handling Regulations, DSE Regulations, Work at Height Regulations).
How should the cost-benefit of recommended control measures be considered?
Answer: By considering whether the cost and effort of the control measure is proportionate to the risk reduction achieved
While safety must not be compromised on cost grounds for significant risks, recommendations should be proportionate. The concept of 'reasonably practicable' requires weighing the cost against the degree of risk. Low-cost, high-impact measures are particularly valuable.
What is the difference between 'risk' and 'hazard' and why is this important for the project?
Answer: A hazard is something that can cause harm; risk is the likelihood and severity of that harm — understanding the difference ensures accurate assessment
Confusing hazard and risk is a common mistake. A hazard (e.g., a wet floor) has the potential to cause harm. Risk is the likelihood that someone will slip and the severity of injury. This distinction is crucial because the same hazard can present different levels of risk depending on controls and exposure.
How should the project demonstrate 'competence' in risk assessment?
Answer: By showing systematic hazard identification, appropriate risk evaluation, knowledge of the hierarchy of control, and practical, justified recommendations
Competence is demonstrated through: thorough, systematic hazard identification using multiple methods, appropriate risk evaluation using a consistent methodology, knowledge and application of the hierarchy of control, practical recommendations supported by evidence and legal references, and a workable action plan.
What should the risk assessment project say about monitoring and review?
Answer: It should include proposals for how the effectiveness of recommended controls will be monitored and when the assessment will be reviewed
A complete risk assessment project should include proposals for: how implemented controls will be monitored for effectiveness (inspections, observations, feedback), triggers for review (changes, incidents, new information), and a scheduled review date. This demonstrates understanding of the ongoing nature of risk management.
How should photographic evidence be used in the risk assessment project?
Answer: To provide visual evidence of hazards, existing controls, workplace conditions, and areas for improvement
Photographs are valuable evidence in the project: they show hazards clearly, demonstrate existing conditions, support written descriptions, highlight areas needing improvement, and provide a baseline for comparison. They add credibility to the assessment and help communicate findings to others.