A client verbally requests a significant change to the approved design mid-project. The professional response is to:
-
A
Implement the change immediately to maintain client satisfaction
-
B
Document the request and issue a formal change order before proceeding
-
C
Refuse the change since the design was already approved
-
D
Complete the original design and add changes at no cost