A firestop scope-of-work change is verbally approved by the GC superintendent. What should the installer do?
-
A
Proceed immediately to avoid schedule delays
-
B
Refuse to proceed until a written change order is issued
-
C
Document the verbal approval in the daily log only
-
D
Ask another subcontractor to complete the changed scope