When a firestop contractor receives shop drawings late, what is the MOST appropriate immediate action?
-
A
Proceed with installation using past project experience
-
B
Issue a formal RFI and document the delay in writing
-
C
Wait without notification until drawings arrive
-
D
Substitute a different listed system without approval