What is 'escalation' in the context of a multi-year firestop contract budget?
-
A
Increasing the scope of work mid-project
-
B
Adjusting projected costs to account for anticipated increases in labor and material prices over time
-
C
Adding contingency for unknown risks
-
D
Changing the contract delivery method