A designer is halfway through a large icon project when the client company is acquired. What contract provision best protects the designer's payment?
-
A
A kill fee clause entitling payment for work completed if the project is cancelled
-
B
A non-compete clause
-
C
A force majeure clause only
-
D
A delivery timeline clause