Under ICC inspection protocols, what action must an inspector take when construction work is covered before a required inspection is approved?
-
A
Issue a stop-work order and require the work to be uncovered
-
B
Accept the work based on contractor certification
-
C
Schedule the next inspection and note the discrepancy
-
D
Allow the work to remain if the contractor provides photos