A building inspector finds that a contractor has covered framing before the required inspection. What is the correct action under the IBC?
-
A
Issue a notice of violation only
-
B
Require the contractor to uncover the work for inspection
-
C
Accept a third-party engineer's letter in lieu of inspection
-
D
Proceed with the next inspection stage