A contractor submits plans that reference an obsolete edition of the IBC. The plan reviewer's ethical and professional responsibility is to:
-
A
Approve the plans since they passed under an older standard
-
B
Reject the plans and require resubmission under the adopted edition
-
C
Approve with a condition that the contractor upgrades later
-
D
Ask the building owner to decide which edition applies