The quantity survey method of cost estimating is considered the most accurate because it:
Select your answer
A
Uses only published national cost indices adjusted to local markets
B
Itemizes all materials, labor, overhead, and profit for every component of construction
C
Applies a single cost-per-square-foot factor to the gross building area
D
Estimates costs by pricing individual installed building components in place