A LIHTC project is behind schedule and at risk of missing the placed-in-service deadline. What is the developer's first recourse?
-
A
Request a placed-in-service extension from the IRS directly
-
B
Contact the state housing finance agency to request an allocation extension or waiver
-
C
Place at least one building in service to preserve the allocation for the entire project
-
D
Return the allocation and reapply in the next funding round