Under LIHTC rules, what is the deadline for meeting the 10% test after receiving a carryover allocation?
Answer: 12 months from allocation date
Projects receiving a carryover allocation must incur more than 10% of the reasonably expected basis within 12 months of the allocation date.
A developer discovers during construction that the site has unexpected soil contamination. Which project management step is the most appropriate immediate action?
Answer: Halt construction, notify the state agency, and engage an environmental consultant
Environmental contamination requires halting affected work, notifying the allocating agency, and engaging a qualified environmental consultant to assess remediation needs.
In a LIHTC project, what document formally establishes the completion date for purposes of the placed-in-service deadline?
Answer: The Certificate of Occupancy issued by the local jurisdiction
A Certificate of Occupancy from the local jurisdiction is the standard evidence used to establish that a building has been placed in service.
A general contractor submits a change order that increases total construction costs by 8%. How does this typically affect the LIHTC basis?
Answer: It may increase eligible basis if the costs are depreciable and part of the qualified building
Depreciable construction costs that are part of the qualified low-income building can increase eligible basis, subject to the allocating agency's review.
Which project management tool is most useful for tracking interdependent construction activities and identifying the critical path in a LIHTC development?
Answer: A Gantt chart with predecessor relationships
A Gantt chart with predecessor relationships enables critical path identification by showing which tasks must be completed before others can begin.
Retainage on a LIHTC construction contract is typically released after which event?
Answer: Substantial completion and resolution of all punch-list items
Retainage is held back during construction to ensure contractor performance and is released after substantial completion and resolution of outstanding punch-list deficiencies.
When a LIHTC project converts from construction loan to permanent financing, which project management milestone triggers this transition?
Answer: Stabilized occupancy, typically defined as 90% or 93% occupancy for a set period
Permanent loan conversion is typically triggered when the project achieves stabilized occupancy, commonly defined as 90โ93% occupancy maintained for 90 consecutive days.