A project manager on a hospital expansion is pressured by the owner to skip a required interim life safety inspection to avoid schedule delays. The ethical response is to:
-
A
Skip the inspection if the owner accepts the risk in writing
-
B
Require the inspection to proceed regardless of schedule pressure
-
C
Delegate the decision to the general contractor
-
D
Proceed and conduct the inspection retroactively after work is complete