When a Potential Change Order (PCO) is issued in healthcare construction, what does it signify?
-
A
Final approval of a scope change
-
B
A preliminary identification of a change that may affect cost or schedule, pending negotiation
-
C
Authorization to stop work on a disputed item
-
D
Rejection of the contractor's change request