GSA Specialist Federal Acquisition Regulations 3 — Questions and Answers
Question 1: Under FAR 6.302-1, a sole source award may be justified when:
- Only one responsible source exists and no other supplies or services will satisfy agency requirements (Correct answer)
- The contracting officer prefers a specific vendor due to past performance
- The acquisition is under the simplified acquisition threshold
- The requirement is classified as critical infrastructure
Correct answer: Only one responsible source exists and no other supplies or services will satisfy agency requirements
FAR 6.302-1 permits other than full and open competition only when only one responsible source exists and no other supplies or services will satisfy agency needs.
Question 2: What is the primary distinction between a 'fixed-price' and a 'cost-reimbursement' contract type?
- Fixed-price contracts require more oversight; cost-reimbursement contracts do not
- In a fixed-price contract the contractor bears cost risk; in cost-reimbursement the government bears most cost risk (Correct answer)
- Fixed-price contracts are only used for services; cost-reimbursement for supplies
- Cost-reimbursement contracts always include incentive fees
Correct answer: In a fixed-price contract the contractor bears cost risk; in cost-reimbursement the government bears most cost risk
Under fixed-price contracts the contractor assumes cost risk and profits from efficiency; under cost-reimbursement contracts the government reimburses allowable costs, bearing most of the financial risk.
Question 3: Which FAR part governs the acquisition of commercial items and encourages their use to streamline procurement?
- FAR Part 8
- FAR Part 12 (Correct answer)
- FAR Part 15
- FAR Part 19
Correct answer: FAR Part 12
FAR Part 12 establishes acquisition policies for commercial items, requiring contracting officers to use commercial item procedures to the maximum extent practicable.
Question 4: A contractor submits a request for equitable adjustment (REA) after encountering a differing site condition. Under FAR 52.236-2, which party bears the burden of proving entitlement?
- The government, because it owns the site
- The contractor, who must demonstrate the condition differed materially from what was indicated in contract documents (Correct answer)
- A neutral third-party arbitrator
- The subcontractor who discovered the condition
Correct answer: The contractor, who must demonstrate the condition differed materially from what was indicated in contract documents
The contractor bears the burden of proving that a differing site condition existed, that it was materially different from what the contract indicated, and that it caused additional costs.
Question 5: Under FAR 9.104-1, which of the following is NOT a standard for contractor responsibility?
- Adequate financial resources to perform the contract
- Ability to comply with proposed delivery schedule
- Lowest price among all offerors (Correct answer)
- A satisfactory record of integrity and business ethics
Correct answer: Lowest price among all offerors
FAR 9.104-1 standards for responsibility include financial resources, ability to meet schedule, a satisfactory performance record, and business ethics — price is not a responsibility factor.
Question 6: When must a contracting officer synopsize a proposed contract action over $25,000 on SAM.gov under FAR 5.201?
- At least 7 days before issuance of a solicitation
- At least 15 days before issuance of a solicitation (Correct answer)
- Within 3 days after contract award
- Only for contracts over the simplified acquisition threshold
Correct answer: At least 15 days before issuance of a solicitation
FAR 5.201 requires contracting officers to publish a synopsis at least 15 days before issuing the solicitation for acquisitions over $25,000, giving industry time to respond.
Question 7: What is the purpose of the 'Competition in Contracting Act' (CICA) as implemented in FAR Part 6?
- To mandate that all contracts use sealed bidding procedures
- To require full and open competition in federal procurements unless a specific exception applies (Correct answer)
- To limit the number of bidders on any given solicitation
- To restrict foreign contractor participation in U.S. federal contracts
Correct answer: To require full and open competition in federal procurements unless a specific exception applies
CICA, implemented through FAR Part 6, requires federal agencies to use competitive procedures to the maximum extent practicable, with enumerated exceptions that must be documented.