A contractor claims the government's actions amounted to a cardinal change. Which of the following BEST describes a cardinal change?
-
A
A unilateral modification reducing the contract price by 5%
-
B
A change so substantial it is outside the general scope and effectively a new procurement
-
C
A change order issued without a bilateral modification
-
D
An equitable adjustment exceeding 15% of the original contract value