During strategic implementation, a program office identifies a need that was not anticipated in the original acquisition plan. What is the CORRECT course of action?
-
A
Revise the acquisition plan to reflect the changed requirements before proceeding
-
B
Issue a unilateral modification to add the work without updating the acquisition plan
-
C
Process the new need as a separate micro-purchase to avoid delays
-
D
Wait until the next fiscal year to incorporate the requirement into a new contract