A contracting officer is evaluating proposals for a cost-reimbursement contract with a technical performance component. Which of the following is a valid reason to adjust an offeror's proposed cost upward during cost realism analysis?
-
A
The offeror's proposed cost is 5% lower than the independent government cost estimate
-
B
The offeror's technical proposal indicates a more complex approach than reflected in the cost proposal, suggesting understated labor hours
-
C
The offeror has a higher indirect cost rate than competitors
-
D
The offeror failed to include G&A costs in the proposal