Government Procurement Certification Audit & Accountability 2 — Questions and Answers
Question 1: Under FAR Part 42, which agency is primarily responsible for conducting contract audits for defense contractors?
- Government Accountability Office (GAO)
- Defense Contract Audit Agency (DCAA) (Correct answer)
- Office of Inspector General (OIG)
- Defense Contract Management Agency (DCMA)
Correct answer: Defense Contract Audit Agency (DCAA)
The DCAA is responsible for auditing defense contractor accounting systems and costs under FAR Part 42.
Question 2: What is a 'forward pricing rate agreement' (FPRA) used for in government contracting?
- Setting fixed prices for all future contracts
- Establishing agreed-upon indirect cost rates for pricing future proposals (Correct answer)
- Auditing past contract performance
- Determining contractor profit margins
Correct answer: Establishing agreed-upon indirect cost rates for pricing future proposals
An FPRA establishes agreed indirect cost rates between the contractor and government for use in pricing future proposals.
Question 3: Which audit type examines whether a contractor's accounting system is capable of accurately tracking costs by contract?
- Performance audit
- Accounting system audit (Correct answer)
- Incurred cost audit
- Price proposal audit
Correct answer: Accounting system audit
An accounting system audit evaluates whether the contractor's system can adequately segregate and track costs by contract.
Question 4: What is the statute of limitations for the government to assert a claim against a contractor under the Contract Disputes Act (CDA)?
- 3 years from the date of contract award
- 6 years from the date the claim accrues (Correct answer)
- 5 years from contract completion
- 10 years from contract closeout
Correct answer: 6 years from the date the claim accrues
Under the CDA, both the government and contractor have 6 years from when the claim accrues to assert a claim.
Question 5: A contractor submits an incurred cost submission (ICS) that is found to be inadequate. What is the consequence?
- The contract is automatically terminated
- The government may withhold payments until adequate submission is received (Correct answer)
- The contractor is barred from future contracts
- The contracting officer must accept the submission as-is
Correct answer: The government may withhold payments until adequate submission is received
If an ICS is found inadequate, the government may withhold a percentage of payments until the contractor submits an adequate ICS.
Question 6: Under the Truth in Negotiations Act (TINA), what is 'defective pricing'?
- Submitting a bid that is too low to be profitable
- Providing cost or pricing data that was inaccurate, incomplete, or non-current at the time of agreement (Correct answer)
- Failing to submit any cost or pricing data
- Overcharging for materials compared to market rates
Correct answer: Providing cost or pricing data that was inaccurate, incomplete, or non-current at the time of agreement
Defective pricing occurs when certified cost or pricing data submitted was inaccurate, incomplete, or non-current, entitling the government to a price reduction.
Question 7: What does a 'should-cost' analysis involve in government procurement?
- Reviewing contractor invoices for mathematical errors
- Independently estimating what a contract should cost using engineering and cost analysis (Correct answer)
- Comparing bids from multiple offerors
- Auditing contractor labor rates after contract completion
Correct answer: Independently estimating what a contract should cost using engineering and cost analysis
A should-cost analysis is a government evaluation that estimates the realistic cost of performance using detailed engineering and cost analysis techniques.
Under FAR Part 42, which agency is primarily responsible for conducting contract audits for defense contractors?