GMC Project Management Fundamentals 3 — Questions and Answers
Question 1: In agile project management for growth marketing, what is the purpose of a retrospective meeting?
- To plan the upcoming sprint backlog with stakeholders
- To review and improve team processes at the end of each sprint (Correct answer)
- To demo completed work to the product owner and stakeholders
- To estimate story points for future user stories
Correct answer: To review and improve team processes at the end of each sprint
A retrospective focuses on continuous improvement by discussing what went well, what didn't, and how to improve next sprint.
Question 2: A growth team is running multiple simultaneous campaigns. Which project management tool best helps visualize task assignments and capacity across team members?
- Gantt chart
- Resource histogram (Correct answer)
- Network diagram
- Risk register
Correct answer: Resource histogram
A resource histogram shows resource allocation over time, making it easy to spot over-allocation or underutilization.
Question 3: What is a 'project baseline' in the context of growth marketing project management?
- The minimum acceptable performance threshold for a marketing campaign
- The approved version of scope, schedule, and cost against which progress is measured (Correct answer)
- The initial budget proposal before executive approval
- A benchmark derived from competitor campaign performance
Correct answer: The approved version of scope, schedule, and cost against which progress is measured
A project baseline is the approved plan (scope, schedule, cost) used as the reference point to measure and control project performance.
Question 4: Which conflict resolution strategy involves finding a solution that partially satisfies all parties and is commonly used in cross-functional growth teams?
- Forcing
- Smoothing
- Compromising (Correct answer)
- Withdrawing
Correct answer: Compromising
Compromising means each party gives up something to reach a mutually acceptable solution, making it practical for cross-functional teams.
Question 5: A growth marketing project has a Cost Performance Index (CPI) of 0.85. What does this indicate?
- The project is delivering $0.85 of value for every $1.00 spent (Correct answer)
- The project is 15% ahead of its planned schedule
- The team has completed 85% of the total project work
- The project's actual cost is 85% of the budgeted cost
Correct answer: The project is delivering $0.85 of value for every $1.00 spent
CPI = Earned Value / Actual Cost; a CPI below 1.0 means the project is over budget (getting less than $1 of value per $1 spent).
Question 6: Which document formally authorizes a growth marketing project and gives the project manager authority to apply resources?
- Project Management Plan
- Project Charter (Correct answer)
- Statement of Work
- Business Case
Correct answer: Project Charter
The Project Charter is the document that officially authorizes the project and grants the project manager authority to assign resources.
Question 7: In Kanban-style project management for growth marketing, what is the purpose of setting Work-In-Progress (WIP) limits?
- To limit the total number of team members on a project
- To prevent bottlenecks by capping tasks at each workflow stage (Correct answer)
- To set a maximum budget for each marketing channel
- To define the maximum number of projects a team can own annually
Correct answer: To prevent bottlenecks by capping tasks at each workflow stage
WIP limits prevent overloading workflow stages, expose bottlenecks, and improve overall team flow and throughput.
In agile project management for growth marketing, what is the purpose of a retrospective meeting?